Capital Costs
You define obstacle removal costs prior to pit optimization and all other capital costs prior to scheduling.
You can define the following capital costs:
-
Location dependent obstacles: defined by an outline with removal cost attached. All optimization programs starting with Pit Optimizer take these costs into account. To define obstacle removal costs, create a Pit Limits 3D Object with “obstacle” regions and choose this object in Pit Optimizer's Options dialog.
-
Pushback startup costs that affect Scheduling and Mine Flow optimizations (only required in Studio NPVS, not NPVS+), defined in Scheduler’s Capital Costs screen.
-
Location-dependent and startup costs are taken into account during scheduling optimization.
-
All capital costs are included in revenue and NPV calculations whenever they are relevant.